Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000

Spread the love

The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of Trustees meeting Thursday.

The final cost for the capital project is now estimated to be between $250,000 and $260,000, including engineering fees. This is an increase from an earlier estimate of $226,000, which was adjusted to account for several necessary but unforeseen tasks.

According to the update, the project is “mostly completed” after the official turn-on and start date of May 22. A few minor items remain to be addressed in the coming weeks.

The cost increase was attributed to a few changes from the original work estimate. Contractors discovered that old ductwork needed to be properly sealed to ensure the efficiency of the new system. An additional thermostat and zone were also added to improve climate control within the building.

Furthermore, the concrete pad supporting the old HVAC unit had settled over time and required replacement to provide a stable foundation for the new equipment.

The library’s treasurer’s report for April showed the district in a strong financial position to handle such projects, with year-to-date income running 2% over budget while expenses were only at 73% of the budgeted amount with just two months left in the fiscal year.

Latest News Stories

Meeting-Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Ad-Hock-July-22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad-Hock-July-22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting-Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
New-Lenox-Village-Board.1

New Lenox’s Crossroads Sports Complex Opens to Rave Reviews, On Time and Under Budget

NEW LENOX – The newly opened Crossroads Sports Complex is already proving to be a resounding success, according to a report delivered at the New Lenox Village Board meeting on...
New-Lenox-Village-Board.4

New Lenox Waives Over $13,000 in Permit Fees for Park District, Church Projects

NEW LENOX – The New Lenox Village Board unanimously approved waiving more than $13,000 in permit and plan review fees for two significant community projects during its meeting on Monday....
New-Lenox-Police.3

New Lenox Approves Site Plan for MBPRO Truck Repair on Moni Drive

NEW LENOX – The Village Board on Monday approved site modifications for a new truck repair business, MBPRO Services, set to open at 21660 South Moni Drive. The board unanimously...
Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 14, 2025

The New Lenox Village Board of Trustees met Monday to approve site plans for a new business, waive fees for community projects, and hear a glowing report on the new...
Meeting-Briefs

Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for June 10, 2025

The Frankfort Fire Protection District Board of Trustees held a special meeting on June 10 to address two major financial items: the fiscal year budget and a new contract with...
frankfort fire district graphic logo.2

Frankfort Fire District Projects $350,000 Surplus, But Faces Capital Crunch for New Engine

Article Summary: The Frankfort Fire Protection District is on track to end the fiscal year with a $350,000 operating surplus, but officials warn that purchasing a much-needed new fire engine...
frankfort fire district graphic logo.6

Frankfort Fire Trustees Approve New Collective Bargaining Agreement with Firefighters Union

Article Summary: Following a closed-door session, the Frankfort Fire Protection District Board of Trustees unanimously approved a new collective bargaining agreement with Local 4338, which represents the district's firefighters. The...
WCO-PZ-July-15

Crete Township Wins Approval for New Digital Sign at Community Center

Crete Township received approval from the Will County Planning and Zoning Commission on Tuesday for a new digital sign at its community center, a project that required a special use...