Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000
The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of Trustees meeting Thursday.
The final cost for the capital project is now estimated to be between $250,000 and $260,000, including engineering fees. This is an increase from an earlier estimate of $226,000, which was adjusted to account for several necessary but unforeseen tasks.
According to the update, the project is “mostly completed” after the official turn-on and start date of May 22. A few minor items remain to be addressed in the coming weeks.
The cost increase was attributed to a few changes from the original work estimate. Contractors discovered that old ductwork needed to be properly sealed to ensure the efficiency of the new system. An additional thermostat and zone were also added to improve climate control within the building.
Furthermore, the concrete pad supporting the old HVAC unit had settled over time and required replacement to provide a stable foundation for the new equipment.
The library’s treasurer’s report for April showed the district in a strong financial position to handle such projects, with year-to-date income running 2% over budget while expenses were only at 73% of the budgeted amount with just two months left in the fiscal year.
Latest News Stories
 U.S.-EU trade deal includes ceiling for European pharmaceutical imports
 Supreme Court allows Trump to block DEI funding
 Trump to probe Smithsonian museums for ‘woke’ ideology
 Director: Nation’s largest outdoor ag show brings economic impact to central IL
 Will County P&Z Approves Crete Solar Farm, Overruling Township’s General Opposition
 Will County Board Approves Controversial Recovery Retreat in Crete Township Amid Strong Resident Opposition
 Will County P&Z: Green Garden Township Variances Granted in Monee
 Will County P&Z: Manhattan Township Rezoning Approved
 Will County P&Z: Green Garden Township Rezoning Approved Amid Concerns Over Lack of a Final Plan
 Zoning Commission Overrules Staff, Approves Greeen Garden Twp Variance for 3-Acre Agricultural Lot
 Pritzker: Fair maps in Illinois would be ‘disarming’ to Democrats
 NY appeals court overturns Trump’s civil fraud penalty
 Lincoln-Way Board Approves Special Education Co-op Budget Amid Concerns Over Rising Costs