Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000
The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of Trustees meeting Thursday.
The final cost for the capital project is now estimated to be between $250,000 and $260,000, including engineering fees. This is an increase from an earlier estimate of $226,000, which was adjusted to account for several necessary but unforeseen tasks.
According to the update, the project is “mostly completed” after the official turn-on and start date of May 22. A few minor items remain to be addressed in the coming weeks.
The cost increase was attributed to a few changes from the original work estimate. Contractors discovered that old ductwork needed to be properly sealed to ensure the efficiency of the new system. An additional thermostat and zone were also added to improve climate control within the building.
Furthermore, the concrete pad supporting the old HVAC unit had settled over time and required replacement to provide a stable foundation for the new equipment.
The library’s treasurer’s report for April showed the district in a strong financial position to handle such projects, with year-to-date income running 2% over budget while expenses were only at 73% of the budgeted amount with just two months left in the fiscal year.
Latest News Stories
Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for July 15, 2025
Meeting Summary and Briefs: Frankfort Square Park District for July 17, 2025
Frankfort Fire District Faces Tighter Budget, Rising Overtime in FY 2025 Outlook
Your Ultimate Guide to the 2025 Frankfort Fall Fest: Everything to Know for the Nationally-Ranked Event
Frankfort Library Tables Reading Room Project Over Higher-Than-Expected Engineering Costs
Meeting Summary and Briefs: Frankfort Township Board for July 14, 2025
Frankfort Park District Board Approves Pay Raise for Executive Director Gina Hassett
Meeting Summary and Briefs: Summit Hill School District 161 for July 9, 2025
Park District’s BDC Dance Program Earns National Recognition
Frankfort Fire District and Firefighters Union to Discuss Possible Referendum
After Initial Rejection and Tense Debate, Board Reconsiders and Approves Contested DuPage Township Business
Frankfort Fire Board Approves $460,000 Purchase of New Cardiac Monitors