Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000
The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of Trustees meeting Thursday.
The final cost for the capital project is now estimated to be between $250,000 and $260,000, including engineering fees. This is an increase from an earlier estimate of $226,000, which was adjusted to account for several necessary but unforeseen tasks.
According to the update, the project is “mostly completed” after the official turn-on and start date of May 22. A few minor items remain to be addressed in the coming weeks.
The cost increase was attributed to a few changes from the original work estimate. Contractors discovered that old ductwork needed to be properly sealed to ensure the efficiency of the new system. An additional thermostat and zone were also added to improve climate control within the building.
Furthermore, the concrete pad supporting the old HVAC unit had settled over time and required replacement to provide a stable foundation for the new equipment.
The library’s treasurer’s report for April showed the district in a strong financial position to handle such projects, with year-to-date income running 2% over budget while expenses were only at 73% of the budgeted amount with just two months left in the fiscal year.
Latest News Stories
Illinois quick hits: State rep. appointed circuit judge; Bailey to seek rematch with Pritzker
WATCH: IL governor on photo with wanted suspect: ‘No way to vet everybody’
Illinois quick hits: Constitutional amendment would guarantee parental rights
WATCH: Republican leader: says Pritzker budget cut EO a ploy for IL tax increases
Judge’s questions during IL gun ban arguments gives rights advocates ‘hope’
Illinois agencies to post monthly investment reports, lawmaker calls symbolic
Meeting Summary and Briefs: Summit Hill School District 161 for August 13, 2025
Summit Hill 161 Accepts a Dozen Resignations, Approves New Hires
Summit Hill 161 Approves $48K Tech Upgrade, Board Divided on New Teacher Hire
Meeting Summary and Briefs: Frankfort Village Board for September 8, 2025
Frankfort Resident Questions Village’s Lake Michigan Water Survey Process
Meeting Summary and Briefs: Frankfort Public Library District for July 24, 2025