Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000
The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of Trustees meeting Thursday.
The final cost for the capital project is now estimated to be between $250,000 and $260,000, including engineering fees. This is an increase from an earlier estimate of $226,000, which was adjusted to account for several necessary but unforeseen tasks.
According to the update, the project is “mostly completed” after the official turn-on and start date of May 22. A few minor items remain to be addressed in the coming weeks.
The cost increase was attributed to a few changes from the original work estimate. Contractors discovered that old ductwork needed to be properly sealed to ensure the efficiency of the new system. An additional thermostat and zone were also added to improve climate control within the building.
Furthermore, the concrete pad supporting the old HVAC unit had settled over time and required replacement to provide a stable foundation for the new equipment.
The library’s treasurer’s report for April showed the district in a strong financial position to handle such projects, with year-to-date income running 2% over budget while expenses were only at 73% of the budgeted amount with just two months left in the fiscal year.
Latest News Stories
Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for August 19, 2025
Frankfort Library Approves Funds for New Heaters, Tree Removal
Summit Hill 161 Welcomes Will County Sheriff’s Deputy as New School Resource Officer
Meeting Summary and Briefs: Frankfort Square Park District for August 21, 2025
Frankfort Fire Board Adopts FY 2026 Budget Amid Rising Insurance Costs
Meeting Summary and Briefs: Will County Board for September 18, 2025
Library Approves $14,700 for Reading Room Architectural Services
Meeting Summary and Briefs: Frankfort Township Board for August 11, 2025
Summit Hill 161 Board Approves $40 Million Budget for 2025-2026 School Year
Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025
LWSRA Details Services for Residents with Disabilities, Plans ‘Hero Village’ Grand Opening
JJC Moves Forward with Major Technology Overhaul to Modernize College Operations
Meeting Summary and Briefs: Frankfort Park District for August 12, 2025