Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000
The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of Trustees meeting Thursday.
The final cost for the capital project is now estimated to be between $250,000 and $260,000, including engineering fees. This is an increase from an earlier estimate of $226,000, which was adjusted to account for several necessary but unforeseen tasks.
According to the update, the project is “mostly completed” after the official turn-on and start date of May 22. A few minor items remain to be addressed in the coming weeks.
The cost increase was attributed to a few changes from the original work estimate. Contractors discovered that old ductwork needed to be properly sealed to ensure the efficiency of the new system. An additional thermostat and zone were also added to improve climate control within the building.
Furthermore, the concrete pad supporting the old HVAC unit had settled over time and required replacement to provide a stable foundation for the new equipment.
The library’s treasurer’s report for April showed the district in a strong financial position to handle such projects, with year-to-date income running 2% over budget while expenses were only at 73% of the budgeted amount with just two months left in the fiscal year.
Latest News Stories
WATCH: Democratic legislators introduce anti-ICE legislation
Illinois Quick Hits: Grayson gets 20 years for murder
Bill Cassidy, facing Trump-backed challenger, bets on ‘who delivers’
Trump Cabinet meeting: New Fed chair, coal saving lives, Russia and Ukraine
Paul introduces legislation to halt welfare funding for non-citizens
Food companies push back on Pennsylvania bills to ban certain food products
Pritzker, Johnson express concerns about 2028 DNC with Trump in office
Pritzker looks for rules for federal school choice scholarship program
Ex-deputy sentenced to 20 years in prison for killing Sonya Massey
Chicago homelessness on rise; advocates push for change
Will County P&Z Approves Mokena Scrap Drop-Off Despite Municipal Objections
Will County Braces for 6,000-Acre Solar Project; Prepare for ‘Massive’ Solar Hearings